As of spring 2024 Pioneer Energy foresees 24+ months of remaining permitting / development plus approximately 12-18 months of construction. This forecast is contingent upon the project obtaining a power purchase agreement (PPA). The SPP Interconnection queue, currently being improved, is likely to extend this timeline.
On-going: Biological surveys, wetlands study, surveys, avian & bat studies, Interconnection planning, Cultural Studies, layout, permitting process.